A 1-MW data center, reduced to a few signals—and still predictable

A compact model reproduced a simulated data center’s grid-facing power with 0.1441% mean error, then translated those predictions into three-phase electrical

0.1441%: the held-out mean error for a 1-MW data-center surrogate tested on a distinct workload trajectory.

A simulated 1-megawatt data center’s grid-facing power was predicted with a mean error of just 0.1441% on a workload trajectory the model had never seen during training or selection. That is the headline result of a study that asks a practical question for an electricity system increasingly shaped by large AI facilities: can we represent a complicated data center accurately without simulating every converter, cooling drive and internal control loop?

The answer, in this paper, is a qualified yes. The researchers built a compact model from signals available at the facility’s electrical boundary, then translated its predictions into a three-phase load. The result is not a data center in a box, nor proof that a grid operator can already replace detailed engineering models with a few equations. It is a promising way to make repeated power-system studies less computationally demanding while preserving the behavior that matters at the grid connection.

The Science

A data center does not look to the grid like a passive building. Its electricity passes through power converters and an uninterruptible power supply, or UPS, which maintains power to computing equipment when the supply is disrupted. The facility’s observed demand also reflects energy storage, IT workload, cooling systems, site-support equipment and the controls linking them. When AI computing demand shifts, these systems can shape not only how much power the site consumes but how quickly it changes and how it responds to voltage and frequency disturbances.

That complexity creates a modeling problem. A detailed physical model can help explain the underlying mechanisms, but it may require internal parameters that are costly to obtain, proprietary or difficult to reproduce. A surrogate model takes another route: it learns the relationship between measurable inputs and outputs, aiming to reproduce the external behavior without recreating every component. Here, the chosen boundary is the point of common coupling, or PCC—the point where the facility connects to the wider electrical system—and the output of the UPS, which supplies the IT load.

Fig. 1: Simulated data-center boundary and measurement locations. The 0.48-kV PCC meter is upstream of the UPS/IT and facility-load branches and therefore measures the complete facility. The UPS power meter is between the UPS output and the directly connected IT load; no downstream 480/240-V transformer is present. Positive active and reactive power point from the grid or UPS toward the load (improvised and adapted from [6]).
Fig. 1: Simulated data-center boundary and measurement locations. The 0.48-kV PCC meter is upstream of the UPS/IT and facility-load branches and therefore measures the complete facility. The UPS power meter is between the UPS output and the directly connected IT load; no downstream 480/240-V transformer is present. Positive active and reactive power point from the grid or UPS toward the load (improvised and adapted from [6]). Source: Jesus D. Vasquez-Plaza, Sunil Subedi

The study’s simulated facility is rated at 999.7 kilowatts of active power: 769 kW for IT, 180.8 kW for cooling and 49.9 kW for site support. Its nominal power-usage effectiveness, a ratio comparing total facility power with IT power, is 1.30. The PCC meter captures the whole site. The UPS meter captures power delivered to the IT branch. That distinction matters: a grid planner needs the facility’s total demand, while the UPS measurement helps describe the behavior of the computing load itself.

The model uses four inputs: normalized IT demand; deviation in the magnitude of the positive-sequence voltage, the balanced component of the three-phase supply; voltage unbalance, a measure of the imbalance among phases; and frequency deviation. It predicts four outputs: active and reactive power at both the PCC and UPS output. Active power does useful work; reactive power supports changing electric and magnetic fields in equipment and affects how power flows through the grid.

The researchers compared six causal model families. “Causal” here means the model predicts from present and past inputs, not future information. Their procedure also separates data by whole operating trajectories: one profile for fitting, another for selecting the model family, and a third held back for a final test. That is a more demanding check than randomly assigning neighboring time samples from the same event to training and testing, because samples from one trajectory can be highly similar.

The winning model is a low-order nonlinear autoregressive model with exogenous inputs, or NARX. In plain language, it predicts future outputs from selected past outputs and past or present input signals, while adding a small number of nonlinear terms to capture interactions. It was fitted with a ridge penalty, a method that discourages unnecessarily large coefficients. The model’s maximum lag is 20 milliseconds, and it runs at 500 samples per second after the original simulated signals are filtered and downsampled.

What They Found

On the external validation trajectory, the NARX achieved a mean error of 0.1959% across its four outputs, measured against a common 1-MVA base. On the held-out test trajectory, its mean error was 0.1441%. The team reports that this was the best validation and test performance among the six model families. The next-best held-out models were a temporal convolutional network at 0.2849% and a recurrent reservoir model at 0.2866%.

Surrogate error on selection and test trajectories

Mean four-output error on a common 1-MVA base for the selected low-order NARX.

Surrogate error on selection and test trajectories
LabelValue
Validation · Profile 10.1959 %
Held-out test · Profile 30.1441 %

The channel-level test scores show where the model’s remaining errors sit. PCC active power had an RMSE of 0.00300 MW, or 3.00 kW. PCC reactive power had an RMSE of 0.00116 MVAr, equivalent to 1.16 kvar. At the UPS output, active-power RMSE was 0.000855 MW, or 0.855 kW, and reactive-power RMSE was 0.000750 MVAr, or 0.75 kvar. These are absolute errors, not percentages of each channel’s own signal range; that distinction is useful because UPS reactive power is small and centered near zero.

The winning model’s held-out errors

Channel-wise RMSE for Profile 3; each channel is reported in its native power unit, as stated in the paper.

The winning model’s held-out errors
LabelValue
PCC active power0.003 MW
PCC reactive power0.00116 MW
UPS active power0.000855 MW
UPS reactive power0.00075 MW

The test was not a perfect reproduction of conditions represented in fitting. The held-out Profile 3 reached approximately 1.16 times the facility’s normalized IT demand, while the training profile reached about 1.0. That gives the result some value as a workload extrapolation test. But the voltage magnitude remained within a narrow range, approximately 0.966 to 0.991 per unit. The paper therefore does not show how the model performs through major voltage sags, faults or other wide-range grid disturbances.

The authors also built an electrical realization of the model’s predicted PCC power in MATLAB/Simulink. A variable resistive load reproduces active power, while controlled current sources synchronized to the PCC voltage reproduce reactive power. This step matters because a prediction curve alone is not necessarily an electrical load that can interact with a power-system simulation. The interface gives the predicted terminal behavior a three-phase electrical form.

Across two 41-second workload profiles, the interface tracked the NARX commands with active-power RMSEs of 0.604 kW and 1.539 kW, and reactive-power RMSEs of 0.353 kvar and 0.442 kvar. Profile A was an additional pipeline-parallelism workload not used to identify the surrogate; Profile B used a DGX-H100 rack workload profile. The larger active-power error for Profile B still amounted to 0.1539% of the 1-MVA base.

Electrical interface tracking across workloads

RMSE between the three-phase electrical realization and the NARX power commands.

Electrical interface tracking across workloads
LabelValue
Profile A active0.604 kW
Profile A reactive0.353 kW
Profile B active1.539 kW
Profile B reactive0.442 kW

The team reports a fitting and model-selection time of 0.77 seconds for the low-order NARX on its workstation. A neural NARX took 38.64 seconds, while a temporal convolutional network took 575.53 seconds. Those runtimes depend on the machine and implementation, and should not be treated as universal benchmarks. Still, they illustrate why a compact model could be useful when researchers need to run many scenarios, explore grid conditions or embed load behavior in larger simulations.

Fig. 4: Surrogate-model performance. (a)–(d) Measured and low-order-NARX-predicted powers for held-out Profile 3. (e) Channel-wise RMSE for the training, validation, and test trajectories, expressed as percentages of the 1-MVA facility base. Insets in (a)–(d) magnify the common 20–25-s interval.
Fig. 4: Surrogate-model performance. (a)–(d) Measured and low-order-NARX-predicted powers for held-out Profile 3. (e) Channel-wise RMSE for the training, validation, and test trajectories, expressed as percentages of the 1-MVA facility base. Insets in (a)–(d) magnify the common 20–25-s interval. Source: Jesus D. Vasquez-Plaza, Sunil Subedi

Why This Changes Things

Data centers are becoming large, concentrated electricity users, and AI workloads can vary on timescales that static demand assumptions miss. Their grid impact is not simply “a lot of megawatts.” Converter controls and facility subsystems can influence voltage support, stability and the way demand changes after a disturbance. Better behavioral models can help power-system researchers ask more realistic questions about those interactions.

The central contribution is a disciplined compromise between detail and usability. The model does not try to reproduce internal UPS states, individual rack supplies or cooling controls. Instead, it predicts four terminal power quantities from four measured features, including both the complete facility’s response and the UPS-to-IT branch. That is potentially valuable when an operator, researcher or equipment vendor can observe boundary signals but cannot access every internal design parameter.

The trajectory-level split strengthens the claim that the model learned more than a memorized segment of one event. Profile 1 guided model selection, and Profile 3 was reserved for assessment; inputs and outputs were scaled using the fitting profile only. The held-out result therefore offers evidence of transfer to a different simulated operating trajectory, including a higher IT-demand peak than the one used in training. It is not, however, evidence of transfer across different data centers, UPS designs or real-world facilities.

The electrical realization adds another useful layer. In power-system studies, representing a predicted load with an actual three-phase interface can make it easier to test how that behavior couples to the rest of a network model. The reported tracking errors suggest that the simple resistance-and-current-source arrangement can reproduce the surrogate’s commands closely under the conditions tested. This could make behavioral models easier to connect to larger simulations without carrying the computational weight of a detailed facility model.

There is a wider practical implication. As grids absorb more variable generation and larger flexible loads, the quality of demand models affects decisions about stability, interconnection and planning. A model that is fast and explicit about its inputs can help researchers explore more cases. But usefulness depends not only on low prediction error; it also depends on whether the operating range, measurement boundary and assumptions match the question being asked.

What’s Next

The most important limitation is stated plainly by the authors: the electrical test uses PCC voltage measurements from the detailed data-center simulation to drive the surrogate’s voltage features and synchronize its current sources. It demonstrates electrical realization of predicted terminal powers under measured PCC excitation. It does not yet demonstrate an autonomous closed-loop replacement that responds to a changing external grid without the detailed model providing that excitation.

Nor does the study establish performance during severe voltage events. The tested positive-sequence voltage range was narrow, and the authors identify broader grid-disturbance validation as future work. A model trained on ordinary operating trajectories should not be assumed to remain reliable during faults, protection events or operating conditions far outside its data. That is especially important if the model is eventually used to assess stability or grid support.

The evidence is also simulation-based, and the paper describes one nominal 1-MW centralized-UPS facility. Real sites differ in UPS architecture, battery controls, cooling equipment, protection settings and workload behavior. Field measurements across facilities would help determine whether the same four inputs are sufficient, whether model coefficients can transfer, or whether each site needs its own calibration.

A next step would be to put the surrogate into a truly closed-loop network simulation, then test it under wider voltage and frequency changes, additional workload shapes and multiple facility configurations. Researchers could also examine how the model behaves when its inputs move beyond the training range, and whether uncertainty estimates can flag situations where its predictions should not be trusted.

The paper’s promise is therefore specific, not sweeping: a small causal model can reproduce the grid-facing behavior of one simulated data center with very low error across distinct workload trajectories, and its predicted powers can be realized electrically with close tracking. If future work extends that result to disturbances, hardware and autonomous operation, grid planners may gain a practical way to study fast-growing data-center demand without treating every facility as an opaque megawatt block—or reconstructing its entire internal machinery.