Great Britain could cut power-system costs 36% by planning wires and storage together

A model of Great Britain’s grid finds that coordinating batteries with transmission could sharply reduce outages and system costs—even when it builds slightly

97% less expected load shedding: the strongest gain came from planning storage and transmission together.

Great Britain’s electricity system could cut modeled expected load shedding by 97% and total expected system costs by 36% by planning energy storage and transmission together, rather than expanding the grid alone. The striking point is that the coordinated strategy needs 2% less additional transmission capacity than transmission-only planning. Batteries and other storage do not replace the wires that move electricity across the country; they can change when and where the system needs those wires, and help keep supply available when conditions are tight.

That result matters because the two kinds of infrastructure are not usually planned as one portfolio. Transmission investment in Great Britain is regulated and forward-looking. Storage is largely developed by market participants responding to market signals. The study’s joint plan is therefore not a blueprint for a single authority to direct all investment. It is a counterfactual benchmark: a way to estimate what the system might gain if the different decisions were better aligned (Cao et al., 2026).

The researchers also find that the answer depends on which energy transition unfolds. Their Electrification and Efficiency pathway needs 7% more transmission capacity and 45% more storage energy capacity than the Falling Behind pathway. A grid designed around one forecast can therefore be a poor fit for another.

Coordinating investment sharply reduces modeled system burdens

Changes in coordinated planning relative to transmission-only planning, as reported in the paper abstract.

Coordinating investment sharply reduces modeled system burdens
LabelValue
Additional transmission capacity-2 %
Cumulative expected load shedding-97 %
Total expected system cost-36 %

The Science

Shengming Cao, Runsheng He and Waqquas Bukhsh at the University of Strathclyde build a planning model for the Great Britain electricity system from 2030 through 2050. Their central question is practical: when demand and generation may change substantially, how should planners choose the timing and location of transmission upgrades and storage installations?

The model links the National Energy System Operator’s Future Energy Scenarios (FES) to a network representation. FES describes several plausible ways the country’s energy system might evolve, including changes in electricity demand, renewable generation, electrification and hydrogen. It does not, by itself, say which transmission corridors should be reinforced. The paper supplies that missing network-level step by translating scenario projections into investment decisions constrained by the modeled grid.

The network is an enhanced version of GB36, a reduced model that represents the country’s major transmission regions and connections using 36 buses. A bus is a point in the network where generation, demand and transmission lines connect. The authors add two high-voltage direct-current links—the Western HVDC Link and Eastern Green Link 1—and recalibrate existing corridor capacities using published transmission-boundary information. The model then contains 68 transmission corridors.

(a) Original GB36 model National Energy System Operator [].
(a) Original GB36 model National Energy System Operator []. Source: Shengming Cao, Runsheng He

This is a strategic planning model, not a detailed engineering design for a particular line. It uses a simplified representation of power flows called DC optimal power flow. Despite the name, it is not a claim that electricity behaves as direct current across the whole grid. It is a computationally manageable approximation to the network equations, useful when the problem includes many years, uncertain futures and yes-or-no investment choices.

The planning is stochastic: rather than pretending that one future is certain, the framework considers alternative pathways and their implications. It compares transmission-only, storage-only and coordinated investment strategies. The model also reflects the different clocks of the assets. Storage is assumed to become available in its investment year; transmission projects have preparation periods estimated from line length, ranging from one to three years. That distinction matters when a project planned today cannot deliver capacity immediately.

The researchers represent each year from 2030 to 2050 and use a representative 24-hour operating profile to capture variation in demand and renewable generation without simulating every hour of every year. They also include investment costs, a real discount rate of 4.5%, asset lifetimes and residual values beyond the planning horizon. Load shedding—the involuntary interruption of electricity supply—is penalized at £10,000 per megawatt-hour, so the model treats failing to serve demand as costly rather than as a convenient way to balance the system.

What They Found

The clearest comparison is between coordinated planning and transmission-only planning. Joint planning reduces cumulative expected load shedding by 97%. In other words, the model’s expected unserved electricity falls dramatically when storage investment can complement grid expansion. That is a consequential finding: avoiding outages is not only an engineering objective but also a way to avoid the economic and human costs of electricity not being available when needed.

The total expected system cost falls by 36%, with the paper attributing the main reduction to avoided unserved energy. This does not mean every bill or every project cost falls by that amount. It is a modeled system-wide comparison across the investments and operating costs included in the framework. The large effect signals that adequacy—having enough usable electricity in the right place and at the right time—can dominate the economics of a portfolio when shortages are expensive.

At the same time, the coordinated plan requires 2% less additional transmission capacity than the transmission-only strategy. That is a modest reduction in grid build, not a finding that storage makes transmission unnecessary. The two resources do different work. Transmission moves power between regions; storage shifts energy across time. When located and timed sensibly, storage can ease some pressures on network investment and reduce the amount of supply left stranded behind constraints.

The pathway comparison puts uncertainty into sharper focus. The paper reports that Electrification and Efficiency requires 7% more transmission capacity and 45% more storage energy capacity than Falling Behind. The larger storage difference is especially notable. A future with more electrified transport and heating can increase electricity use and alter when demand occurs, while a slower transition has different requirements. The model suggests that storage energy capacity—the amount of energy storage can hold, rather than simply its power rating—may be particularly sensitive to the path chosen.

Electrification and Efficiency raises capacity needs versus Falling Behind

Reported differences in investment requirements between the Electrification and Efficiency pathway and Falling Behind.

Electrification and Efficiency raises capacity needs versus Falling Behind
LabelValue
Transmission capacity7 %
Storage energy capacity45 %

The results also distinguish investment timing from the final portfolio. Transmission preparation periods change when assets must be committed to become available, but the authors report that they do not change the final portfolio in their tested cases. That should not be read as proof that lead times do not matter. If anything, it emphasizes that the same eventual infrastructure can have different adequacy consequences depending on whether it arrives in time.

The paper considers four FES 2025 pathways: Holistic Transition, Electric Engagement, Hydrogen Evolution and Falling Behind. The abstract’s numerical contrast is specifically between Electrification and Efficiency and Falling Behind; the provided paper material does not give all pathway-by-pathway quantities. The overall lesson is not that one scenario can be selected with certainty, but that planning choices should be tested against a range of plausible futures.

Why This Changes Things

A common instinct in energy planning is to focus on the visible bottleneck: if power cannot move from a windy region to a demand centre, build more transmission. But a power system is a set of interacting assets, not a collection of independent shopping lists. Storage may charge when local generation is abundant and discharge when demand rises or a network corridor is constrained. A line upgrade can also change where storage creates value. Optimizing one asset class without the other can therefore miss useful combinations.

That coordination problem is institutional as much as technical. In Great Britain, the regulated network-planning process and the market-led development of storage do not amount to a single joint optimization. The paper’s modeled portfolio shows the potential system value of coordination, but it does not establish that current market signals will deliver the same mix, or that centralized procurement is the only solution. More targeted market rules, planning assumptions or incentives might help storage locate where it supports the system rather than simply where private returns look strongest.

The benchmark also gives decision-makers a way to ask a more precise question than “How much storage do we need?” The relevant questions include where it should connect, what transmission projects it complements, when it should be available, and which futures the plan is intended to withstand. These are questions that matter in many countries facing renewable growth and electrification, even though the exact British network and scenario data cannot simply be transferred elsewhere.

There is an important caveat in interpreting the reported savings. The 97% reduction in expected load shedding is a comparison within this model and its assumptions, not a forecast that real-world outages in Britain will fall by 97%. Expected load shedding depends on how the model represents operating conditions, network constraints, investment options and the high penalty assigned to unserved energy. Likewise, a 36% reduction in modeled system cost is not a guaranteed reduction in consumer bills.

The work nevertheless makes a useful contribution by joining several pieces often treated separately: national pathways, a geographically grounded network, annual investment decisions, and different commissioning schedules for lines and storage. Its network is reduced rather than a full engineering-grade map, and the representative 24-hour profile cannot capture every weather event or operating contingency. Its investment limits and cost assumptions also shape the portfolios it can find. Those boundaries make the results a planning signal, not a final construction list.

What’s Next

The next step is to test how robust the coordination benefit remains under more detailed operating conditions. Multiple weather years, more granular hourly profiles, outages and security constraints could reveal where storage and transmission remain complements—and where they compete. Updated cost and siting assumptions would also help distinguish a general planning insight from a result tied to a particular set of inputs.

There is also a governance question. If coordinated planning is valuable in a model where transmission and storage are separate investment decisions, how can institutions capture that value without assuming that one body must control both? The study points toward better alignment of planning and market signals, but it does not prescribe a specific reform. That is a policy problem as much as an optimization problem.

The broader message is grounded but hopeful: a more reliable low-carbon grid may not require simply building more of every asset. It may require building the right combination, in the right places, and early enough for the future that actually arrives. By putting wires and storage into the same planning frame, Cao and colleagues offer a way to see—and quantify—the value of making those decisions together.