The cheapest route to more AI may be moving the work, not the power

The cheapest route to more AI may be moving the work, not the power
Over 11 Million Hourly operations modeled
More Than 95% Delayed centres online by 2030
Canada, Nordics, Arabian Peninsula Preferred regions
38% carbon emissions reduced
44–47% construction costs reduced
34–67 GW high-voltage capacity avoided

AI’s next data centres may not need to wait for new power lines. They could be built where electricity is plentiful, then connected to users by moving computation over fibre-optic cables. In the scenarios studied by Jiawei Qu and colleagues, this approach cut data-centre construction costs by 44–47%, reduced emissions by 38%, and could bring more than 95% of connection-delayed projects online in 2030. It also avoided the need for 34–67 gigawatts of high-voltage transmission capacity—roughly comparable to Italy’s peak electricity demand (Qu et al., 2026).

That is a striking reframing of the AI infrastructure problem. The conventional response to a data-centre bottleneck is to get more electricity to the place where the computers are planned. This paper asks whether it is sometimes better to send the computing task to a place that already has power, water, land and a workable connection to the internet.

The distinction matters because electricity is difficult to move over long distances. New transmission lines take years to plan, permit and build, and local grid constraints can hold up data-centre projects even when developers have financing and equipment ready. Digital information, by contrast, can travel through existing fibre networks at the speed of light. If an AI workload can be scheduled flexibly, its servers need not be located beside the user or the company that owns the data.

The paper’s title gives the core idea a memorable shorthand: move bits instead of watts. But this is not a claim that fibre can replace power grids, or that every AI task can be shifted freely around the world. It is a global planning framework that identifies where additional computing capacity could be placed and how its workloads could be routed, while accounting for energy, water, network connectivity, land and financing risk.

The Science

Qu, Shi, Hou, Jia and Yan examine a mismatch between where data centres are being planned and where the infrastructure to power them is readily available. Demand for AI computing is rising rapidly. Large facilities draw substantial and continuous electricity, while grid connections and high-voltage transmission infrastructure can be slow to expand. A project can therefore face a queue not because the world lacks electricity in general, but because it cannot obtain enough power at its chosen location.

The authors propose treating computation as spatially flexible. A data centre in one region can perform a workload for a user elsewhere, with the results travelling through fibre-optic networks. In practical terms, some computing demand could be directed to places with more suitable energy and infrastructure conditions instead of concentrating all new capacity near existing clusters of users and businesses.

This idea is familiar in a limited form: cloud computing already lets people use remote servers. The paper’s contribution is to elevate that principle into a global infrastructure-planning strategy. It asks how much proposed data-centre capacity could be relocated, where it should go, and what the consequences would be for cost, emissions and transmission requirements.

The location decision is not based on electricity alone. A data centre needs a reliable supply of power, but it also uses water for cooling in many designs, occupies land, depends on a sufficiently capable digital connection and must be financeable. Those factors can pull in different directions. A place with abundant low-carbon electricity may be far from major fibre routes; a well-connected location may face water stress or expensive construction. A site that looks attractive on one map may be difficult or risky on another.

The researchers built a global framework that evaluates these interacting constraints at subnational resolution. They ran more than 11 million hourly operational simulations, testing how data-centre deployment and operation might work under multiple development and climate-policy scenarios. The hourly modelling matters: electricity supply, demand and carbon intensity change over time, so a site’s annual average can conceal periods when power is scarce or more emissions-intensive.

The abstract does not provide the detailed definitions of each scenario, the underlying regional datasets, or the assumptions about which workloads can be moved and how much latency they can tolerate. Those details are important for interpreting the precise estimates. The headline results should therefore be read as outcomes of a modelled framework, not as a forecast that every project will automatically relocate or that all AI services can be served from distant facilities.

The paper’s central framework links candidate data-centre locations with energy resources, water, land, financing risk and fibre-optic connectivity. Its organising question is not simply where electricity is cheapest, but where computing can be built and reliably connected as a whole.

What They Found

Across the development and climate-policy scenarios examined, shifting workloads through global data-transfer networks reduced new data-centre construction costs by 44–47% compared with the study’s reference approach. The size of the range signals that outcomes vary across scenarios, but even the lower end suggests that location flexibility can change the economics substantially. Instead of building only where demand is concentrated, developers could consider regions where the combined conditions for construction and operation are more favourable.

The model also found a 38% reduction in carbon emissions. That result follows from the possibility of locating computation in areas with access to less carbon-intensive energy, rather than serving all demand from places where electricity may be constrained or more emissions-intensive. It is a modelled system-level result; it does not mean every relocated data centre would be powered entirely by renewables, or that moving a workload is emissions-free. The network and the receiving facility still consume resources, and the reported figure depends on the paper’s scenario assumptions.

Potential reductions in cost and emissions

Reported reductions across the study’s scenarios. Construction cost is expressed as a range; emissions as the reported reduction.

Potential reductions in cost and emissions
LabelValue
Construction costs (low end)44 % reduction
Construction costs (high end)47 % reduction
Carbon emissions38 % reduction

This chart shows the paper’s reported construction-cost reduction range and emissions reduction. The abstract gives the outcomes as scenario results, rather than a detailed set of values for every individual scenario.

The transmission result makes the infrastructure implications easier to picture. The framework avoided 34–67 gigawatts of high-voltage transmission capacity. A gigawatt is a measure of power, or the rate at which electricity can be delivered. The paper compares this range with Italy’s national peak electricity demand, making clear that the potential avoided grid requirement is not a marginal adjustment. It is of a scale associated with powering a large national system at its busiest moment.

High-voltage transmission capacity avoided

The model estimates a range of high-voltage transmission capacity avoided by siting data centres where conditions are favourable and routing workloads over fibre.

High-voltage transmission capacity avoided
LabelValue
Low estimate34 GW
High estimate67 GW

The study estimates 34–67 GW of high-voltage transmission capacity could be avoided by routing workloads to data centres in better-supplied locations. The range is comparable in magnitude to Italy’s national peak demand, according to the authors.

Perhaps the most immediate result is the estimate that the approach could bring more than 95% of data centres delayed by grid connections online in 2030. That is not the same as saying 95% of all planned data centres would be built, or that their connection problems would disappear. It refers specifically to connection-delayed facilities in the modelled 2030 setting, under a strategy that allows data-centre capacity and workloads to be placed elsewhere.

The model identifies Canada, the Nordic countries and the Arabian Peninsula as preferred regions for development. These are not interchangeable locations, nor does the abstract say that every site in each region is suitable. Their appearance reflects the framework’s combined assessment of resources and constraints. The finding is therefore best understood as a regional signal: under the studied assumptions, these areas stand out as candidates for additional capacity when computing can travel over networks.

Connection-delayed data centres potentially enabled in 2030

The proportion of grid-connection-delayed data centres that the framework could bring online in 2030, according to the paper’s abstract.

Connection-delayed data centres potentially enabled in 2030
LabelValue
Potentially brought online95 %

The paper names Canada, the Nordic countries and the Arabian Peninsula as preferred locations for data-centre development in its global framework. The abstract does not report comparable regional scores or capacity totals, so this figure presents the locations qualitatively rather than inventing rankings.

Together, these results suggest that data-centre planning need not follow the same geography as electricity demand. The grid can remain constrained in one place while the digital service is delivered from another. In that sense, fibre connectivity becomes more than a communications convenience: it can act as a way of accessing energy resources located far from the user.

Why This Changes Things

The usual mental model for digital infrastructure is local: users generate demand, data centres are built nearby, and the grid must supply them. The paper offers a second model. Some demand can be served by remote facilities, allowing the location of computation to respond to the geography of electricity, water and land. That does not remove the need for local power infrastructure, but it could reduce the amount that must be built in the most congested areas.

This matters because transmission is a large, physical project. New power lines require corridors, permits, engineering and coordination across jurisdictions. They can be delayed by public opposition and competing land uses, even when their purpose is clear. If flexible computing demand can be located elsewhere, a portion of the infrastructure burden may be avoided rather than merely postponed.

The possible gains also connect directly to climate policy. Data centres can lock in demand for decades, so where they are built can influence both the electricity system and emissions. If operators can use fibre to direct workloads toward regions with lower-carbon power, digital growth may fit more easily with decarbonisation goals. The paper’s 38% result gives a sense of the potential in its scenarios, but actual outcomes will depend on the energy mix at the chosen sites, the timing of workloads and the emissions associated with network and facility operation.

There is a broader lesson here about infrastructure. A fibre network and an electricity network are often planned as separate systems, with different institutions and investment decisions. Yet digital connectivity can change where electricity is needed. If a data centre can be situated near available power and connected to users through fibre, the communications system partly substitutes for an expansion of the power system at the original location. Coordinated planning could therefore reveal options that sector-by-sector decisions miss.

The approach could also alter the politics of data-centre development. Regions that have been peripheral to the AI economy may attract investment because they have energy resources, suitable land and network access. That could mean jobs, tax revenue and new digital infrastructure. It could also raise questions about who benefits, who bears the local environmental costs, and whether new facilities compete with households and other industries for power or water. “Preferred” in a global model is not the same as “socially agreed” at a local site.

Nor is distance free. Moving bits requires a reliable fibre route and enough network capacity. Workloads differ in how much delay they can tolerate. A task that can run overnight or return results later is a better candidate for relocation than an interactive service that must respond almost instantly. Some computing also involves sensitive data or rules that restrict cross-border transfer. The abstract’s headline results do not tell us how extensively the model represents these operational, regulatory and security limits.

Water is another reason not to reduce the paper to a search for cheap electricity. Data centres need cooling, and the water implications of a site depend on its climate, cooling technology and local water availability. A location with plentiful energy may still be a poor choice if it places pressure on a scarce water supply. The framework’s inclusion of water, land and financing risk is valuable precisely because it recognizes that an energy-only map can give the wrong answer.

The study’s central proposal is therefore not “put data centres anywhere.” It is to treat the entire chain—from power generation and cooling to land, fibre and financing—as a connected system. A remote site is useful only if the facility can be built, powered, cooled and connected, and if the workloads can actually be transferred there.

What’s Next

The paper presents a compelling case for computational mobility as one tool for easing grid bottlenecks, but its results invite a closer look at the assumptions beneath the headline figures. The abstract reports more than 11 million hourly simulations, yet it does not give the workload mix, latency limits, transmission accounting, or regional capacity values needed to assess every result independently. The detailed methods and supplementary data will determine how much of the estimated potential translates into deployable projects.

A next step is to distinguish workloads by their flexibility. Training runs, batch analysis and some background services may be schedulable across regions. Real-time applications may not be. Data governance can also constrain where work happens, while network failures or congestion could make a distant facility less dependable than the model assumes. A practical rollout would need to specify which tasks can move, how quickly they can move, and what safeguards preserve performance and data security.

The headline locations also deserve local analysis. Canada, the Nordic countries and the Arabian Peninsula are broad regions, not ready-made development sites. Planners would need to examine local grids, water basins, land-use conflicts, community priorities, renewable-energy availability and the capacity of existing fibre routes. An energy advantage at national scale may disappear at the level of a particular town or substation.

Finally, the policy question is not only whether fibre can substitute for transmission, but how to coordinate the two. Some grid upgrades will remain essential, especially for homes, industry and services that cannot move. The more useful question is where a new line is necessary, where it can be delayed, and where flexible data-centre siting offers a cheaper or faster alternative. That requires energy regulators, network operators, data-centre developers and local governments to plan together rather than optimize separate maps.

The promise of “moving bits instead of watts” is not that the physical world disappears behind the cloud. It is that a digital service can sometimes be delivered without insisting that its electricity be delivered to the same place. If the model’s potential survives closer scrutiny, fibre networks could become part of the toolkit for managing the energy demands of AI—helping societies build computing capacity faster while avoiding some costly grid expansion and emissions. The next phase is to discover which workloads, locations and communities make that trade genuinely beneficial.