← News
Tech for Good Tech for Good Frontiers

The fastest power source may beat the cheapest one for AI

The fastest power source may beat the cheapest one for AI
18% Versus AC Designs Lifetime energy cost cut
Continental U.S. Locations Study scope
Deployment Speed Main factor
85% locations where lowest-cost
18% lifetime energy cost reduction
55% natural gas timeline locations

An AI data center can lose more by waiting for electricity than it saves by buying cheaper electricity. In a model of facilities across the continental United States, DC-coupled solar-and-battery microgrids became the lowest-cost option in 85% of locations once the researchers counted the computing capacity forgone while a project waited to power up. Without that time penalty, these systems were rarely the cheapest source of energy.

That is the paper’s unsettling economic twist: the best power plant for an AI company may not be the one with the lowest price per kilowatt-hour. It may be the one that gets chips working sooner. Newkirk and colleagues compare grid interconnection, natural-gas generation, and solar-plus-storage systems, asking what happens when energy costs and time-to-compute are put on the same ledger (Newkirk et al., 2026).

The stakes extend beyond the companies buying electricity. Large data centers can require hundreds of megawatts, and proposed AI facilities may reach gigawatt scale. The grid connections, turbines, transformers, and approvals they need are already in tight supply. Faster self-supply could help firms build, but it could also bring new questions about land, emissions, reliability, and who pays for shared infrastructure.

Figure 1: Analytical framework. For a given quantity of chips, workload (in this research empirically calibrated to AI training) and location (climate, solar resource, gas price, grid rate, and interconnection queue), we build an hourly facility load combining IT demand with climate-driven cooling (PUE). We then size and dispatch three islanded architectures, AC solar+storage, DC solar+storage, and islanded natural gas with diesel backup, and compare them against grid interconnection. Each deliver equivalent energy service at equivalent reliability through an explicitly modeled power-conversion path. Each option is assessed on two axes: its unadjusted levelized cost of energy ($/kWh) and the value of compute forgone during construction (set by deployment speed and chip-hour value). Their sum, a speed-adjusted cost (LCOEadj), determines the preferred option, which varies with location, scale, technology, and the value of time.
Figure 1: Analytical framework. For a given quantity of chips, workload (in this research empirically calibrated to AI training) and location (climate, solar resource, gas price, grid rate, and interconnection queue), we build an hourly facility load combining IT demand with climate-driven cooling (PUE). We then size and dispatch three islanded architectures, AC solar+storage, DC solar+storage, and islanded natural gas with diesel backup, and compare them against grid interconnection. Each deliver equivalent energy service at equivalent reliability through an explicitly modeled power-conversion path. Each option is assessed on two axes: its unadjusted levelized cost of energy ($/kWh) and the value of compute forgone during construction (set by deployment speed and chip-hour value). Their sum, a speed-adjusted cost (LCOEadj), determines the preferred option, which varies with location, scale, technology, and the value of time. Source: Alex C. Newkirk, Daniel L. Gerber

The Science

The researchers built a technoeconomic model for AI training facilities at different locations and scales. They compared four options: conventional grid connection; an islanded natural-gas plant with diesel backup; and solar photovoltaic panels plus batteries, configured with either AC or DC power distribution. “Islanded” means the facility operates independently of the public grid. The options were designed to provide equivalent energy services at equivalent reliability, so the comparison would not simply reward one system for doing less.

A data center’s electricity bill is not just the power consumed by its chips. Cooling systems also draw electricity, and their needs depend on local weather. The model estimates hourly facility demand using a near-constant training workload and climate-driven cooling performance. It represents an 8-GPU node equivalent drawing an average 7.3 kilowatts, then scales facilities by GPU count. A 100,000-GPU example requires roughly 131 megawatts of design capacity, including cooling and contingency margins.

The power route matters, too. Solar panels and batteries produce and store direct current, or DC. The U.S. grid distributes alternating current, or AC. Converting between them requires power electronics, and each conversion loses some energy as heat. DC coupling connects solar, storage, and suitable facility loads with fewer conversion steps. The researchers model these paths stage by stage rather than assigning every system one generic efficiency number.

The study also accounts for geography. A hot, humid site needs more mechanical cooling than a cooler one; solar output, natural-gas prices, grid rates, and interconnection delays vary by place. For solar-and-storage designs, the team simulates hourly weather and power flows, and models battery aging and replacement. For gas, it evaluates commercially available turbine configurations, including performance penalties at partial load and in hot conditions.

Then comes the paper’s distinctive move. The authors estimate the value of compute that could have run during construction, based on the project’s deployment timeline and the economic value assigned to a GPU-hour. They combine this “speed premium” with the levelized cost of energy, or LCOE: the lifetime cost of building and operating a system divided by the energy it delivers. Their speed-adjusted measure makes a delayed grid connection comparable with an earlier, potentially more expensive microgrid.

What They Found

The first result is a practical engineering advantage. Across modeled U.S. locations, DC-coupled solar-plus-storage reduced lifetime energy costs by an average of 18% compared with AC counterparts, equivalent to $0.09 per kilowatt-hour in the paper’s reported average. Fewer conversion stages help explain why. The difference was not identical everywhere: the authors report that its magnitude depends partly on solar resources and how much generation and storage a location needs.

Figure 3: Cost advantage of DC-coupled systems over AC counterparts for 100,000 GPUs at 99% uptime across all modeled continental U.S. locations. Skew in the absolute distribution reflects variation in sensitivity to solar-to-load and battery-to-load path efficiency by location. Scale of DC advantage generally increases in locations with lower quality solar resources as marginal path efficiencies provide returns for highly overbuilt systems. In regions with substantial and consistent solar resources, both AC and all-DC microgrids can scope more aggressively, shrinking but not eliminating the DC cost advantage.
(A) Percentage cost advantage distribution. Mean DC advantage is 18% of total cost of ownership for a given location.
(B) Absolute cost advantage distribution. Mean DC advantage is $0.09 / kWh.
Figure 3: Cost advantage of DC-coupled systems over AC counterparts for 100,000 GPUs at 99% uptime across all modeled continental U.S. locations. Skew in the absolute distribution reflects variation in sensitivity to solar-to-load and battery-to-load path efficiency by location. Scale of DC advantage generally increases in locations with lower quality solar resources as marginal path efficiencies provide returns for highly overbuilt systems. In regions with substantial and consistent solar resources, both AC and all-DC microgrids can scope more aggressively, shrinking but not eliminating the DC cost advantage. (A) Percentage cost advantage distribution. Mean DC advantage is 18% of total cost of ownership for a given location. (B) Absolute cost advantage distribution. Mean DC advantage is $0.09 / kWh. Source: Alex C. Newkirk, Daniel L. Gerber

The more consequential result appears when the clock is priced. Under the baseline assumptions, DC solar microgrids had the lowest speed-adjusted cost in 85% of modeled locations. Grid connection remained preferable in the remaining 15%, particularly where electricity was relatively cheap and interconnection approvals comparatively quick. In other words, solar was not winning because its raw energy cost was generally lowest. It was winning because it could be deployed sooner.

That conclusion is sensitive to how quickly gas plants can be built. The baseline case assumes four years for turbine delivery and plant construction. In a faster, 36-month natural-gas scenario, DC solar remained preferred in about 55% of locations; gas was preferred in about 35%, and grid connection in roughly 9%. The geography changes in a coherent way: gas becomes more attractive in some solar-poor regions, while DC solar remains widely favored. These shares are rounded as reported in the paper.

Figure 6: Minimum speed-premium LCOE for 100,000 GPU facilities across the continental United States. Color indicates LCOE magnitude; hatching shows lowest-LCOEadj technology. Maps vary by natural gas deployment speed assumptions, with the top panel (A) showing the baseline case of 4 year combined turbine delivery and plant construction time, and the bottom panel (B) showing the accelerated 3 year case.
(A) Baseline construction timelines: DC solar is the lowest LCOEadj architecture in 85% of locations due to rapid deployment despite higher unadjusted energy costs. Grid interconnection remains preferred in regions (15% of locations) combining poor solar resources, low industrial electricity rates, and abbreviated approval timelines.
(B) Accelerated 36-month natural gas timelines: DC solar (solid) is preferred in ∼55% of locations. Natural gas (dots) is preferred in ∼35% of locations, forming coherent regional deployments in solar-poor areas (upper Midwest, Appalachian Basin, Pacific Northwest). Grid interconnection (diagonal hatching) remains optimal in ∼9% of locations. Even under this aggressive scenario, DC solar microgrids remain the most widely preferred option.
Figure 6: Minimum speed-premium LCOE for 100,000 GPU facilities across the continental United States. Color indicates LCOE magnitude; hatching shows lowest-LCOEadj technology. Maps vary by natural gas deployment speed assumptions, with the top panel (A) showing the baseline case of 4 year combined turbine delivery and plant construction time, and the bottom panel (B) showing the accelerated 3 year case. (A) Baseline construction timelines: DC solar is the lowest LCOEadj architecture in 85% of locations due to rapid deployment despite higher unadjusted energy costs. Grid interconnection remains preferred in regions (15% of locations) combining poor solar resources, low industrial electricity rates, and abbreviated approval timelines. (B) Accelerated 36-month natural gas timelines: DC solar (solid) is preferred in ∼55% of locations. Natural gas (dots) is preferred in ∼35% of locations, forming coherent regional deployments in solar-poor areas (upper Midwest, Appalachian Basin, Pacific Northwest). Grid interconnection (diagonal hatching) remains optimal in ∼9% of locations. Even under this aggressive scenario, DC solar microgrids remain the most widely preferred option. Source: Alex C. Newkirk, Daniel L. Gerber

The economics also shift with facility size. In an eastern Colorado example, the modeled natural-gas LCOE falls by $0.15 per kilowatt-hour across the range of design loads shown, reflecting economies of scale: a larger plant spreads fixed costs over more output. Solar-plus-storage costs vary much less with nameplate capacity in that comparison. But a low energy price does not automatically make gas the preferred choice if it takes longer to procure and construct.

The paper offers a way to interpret the time argument: the GPU-hour value at which a company is indifferent between DC solar and grid power. Across locations, the median threshold is $1.61 per GPU-hour. The authors’ baseline assumption is $2.40 per GPU-hour. Under that assumption, the economic value of getting compute online sooner is high enough to make DC microgrids competitive with grid interconnection in much of the country. This is a modeled break-even, not a measured market price for AI computing.

Figure 7: Value of a chip-hour at which firms would be indifferent between DC-coupled microgrids and grid interconnection. Holding interconnection timelines at baseline (state-specific, 2.5-5 years). Color indicates indifference utility in $/GPU-hour; white contour marks the baseline assumption ($2.40/hr). Blue regions show where DC solar dominates even at low GPU values due to favorable solar resources and/or slow grid interconnection. The median indifference utility is $1.61/hr. Orange/red regions (concentrated in New England and parts of Texas) show where grid remains competitive even at high GPU opportunity costs due to cheap electricity and fast interconnection. Most of continental U.S. lies below $2.40/hr (blue spectrum), indicating DC microgrids are preferable to grid interconnection when valuing deployment speed even at lower GPU value.
Figure 7: Value of a chip-hour at which firms would be indifferent between DC-coupled microgrids and grid interconnection. Holding interconnection timelines at baseline (state-specific, 2.5-5 years). Color indicates indifference utility in $/GPU-hour; white contour marks the baseline assumption ($2.40/hr). Blue regions show where DC solar dominates even at low GPU values due to favorable solar resources and/or slow grid interconnection. The median indifference utility is $1.61/hr. Orange/red regions (concentrated in New England and parts of Texas) show where grid remains competitive even at high GPU opportunity costs due to cheap electricity and fast interconnection. Most of continental U.S. lies below $2.40/hr (blue spectrum), indicating DC microgrids are preferable to grid interconnection when valuing deployment speed even at lower GPU value. Source: Alex C. Newkirk, Daniel L. Gerber

Location-specific energy costs matter independently of speed. In southeastern California, strong solar resources and high electricity prices favor DC solar across the modeled utilization range. In Houston, the model finds natural gas becomes cheaper than DC solar above 77% annual uptime, although both are more expensive than the grid in the example. In eastern Washington, inconsistent solar makes high-reliability solar-plus-battery power more costly. These examples underline that there is no single best architecture for every facility.

Why This Changes Things

The analysis puts a price on something executives already treat as precious: time. AI companies compete to train and deploy models, and a facility that is ready months earlier can produce computing services while a rival is still waiting for an interconnection agreement or turbine. That makes the usual power-sector comparison—how much does each kilowatt-hour cost?—incomplete for a business whose valuable asset is computation.

The broader infrastructure context is real. Grid interconnection queues can stretch beyond five years in some regions, while turbine delivery timelines have also lengthened. Components such as transformers and high-voltage equipment face backlogs. A microgrid can bypass some of these bottlenecks, though it cannot make every permitting, construction, supply-chain, or land constraint disappear.

DC distribution is also a reminder that data centers are not ordinary electricity consumers. Their core computing chips already use DC internally, and their electricity costs dominate operating expenses. If a facility’s power architecture can avoid unnecessary conversions, small efficiency gains can compound across a large, continuously operating load. The study connects that internal design choice to the generation and storage system outside the building.

But faster construction has consequences. A DC solar microgrid requires a large solar and battery installation, and an islanded natural-gas plant burns fossil fuel. A project can reduce pressure on a delayed grid connection while creating other local demands, including land use, fuel infrastructure, and potential emissions. The paper’s central comparison is technoeconomic, not a full accounting of every environmental or community impact. Nor does its result mean that microgrids automatically reduce household bills or relieve grid constraints; those outcomes depend on how projects interact with the surrounding system.

The work’s strongest contribution may be methodological. Its open-source framework brings workload, climate, conversion losses, battery degradation, reliability, and construction timelines into one comparison. That can help developers, utilities, and policymakers see which assumptions actually change a decision. It also makes clear that the answer is conditional: lower energy cost, faster delivery, facility scale, local solar, gas prices, and the value of compute all pull in different directions.

What’s Next

The key uncertainty is the value of a GPU-hour. The paper uses a baseline assumption of $2.40 per GPU-hour and reports a median break-even value of $1.61. Those values make the time premium tangible, but a real company’s return on earlier computing will depend on what the chips do, how much they are used, the value of the models or services produced, and whether demand is waiting. If compute is underused, the advantage of early energization shrinks.

Construction schedules are equally consequential. The paper tests a faster gas timeline, and the preferred option shifts substantially. Real projects may experience delays in permits, equipment delivery, site preparation, and workforce availability; timelines can vary by region and project. Better evidence from completed projects would sharpen the comparison, as would analysis of hybrid strategies that begin with one power source and later connect to the grid.

There are also questions beyond cost and reliability. How much land and water do different designs require? What are the emissions consequences of gas generation compared with the electricity a grid connection would supply? How should utilities allocate the cost of grid upgrades when a large load can self-supply at first, then seek a connection later? Those questions determine whether the fastest private solution is also the best public one.

For now, the paper challenges a common instinct: to judge energy infrastructure by the price of its output alone. In the AI boom, a power source is valuable not only for what each kilowatt-hour costs, but for how soon it lets a facility turn electricity into computation. If those timelines remain tight, speed may become a form of energy economics—and a decisive force shaping where, and how, the next generation of data centers gets built.